HLC(HalalChain) Blockchain Project Status Report — Week 50

  • BY:HALALCHAIN
  • May 12, 2019
HLC(HalalChain) Blockchain Project Status Report — Week 50

Work Completed

Underlying Public Chain Development:

•Completed development and debugging of P2P network.

•Completed P2P-based main node test.

 

DAG Development:

•Researched AvivYaish’s PHANTOM realization.

 

Wallet& Browser Development:

•Tested IOS wallet’s function and fixed its bug.

•Located server api instability problem and drafted solution.

•Created new branches under the complete main network code to integrate wallet related functions.

•Studied a solution of android wallet’s fluency.

•Researched ETH’s Dapp implementation logic.

•Researched wallet cross-chain logic.

 

Mining& Mine Pool Development:

•Completed the mining pool whole network computing power data capture development.

•Modified backstage payment management and test bugs.

•Tested payment backstage PPLNS model.

•Cockoo algorithm implementation and source code research.

•Compiled and deployed the grin test node.

•Studied grin code to see pow implementation in grin.

 

Work in Progress Next Week

Underlying Public Chain Development:

•Completing main net, wallet and mining coordination and integration.

•Establishing local test environment and multi-node development.

 

DAG Development:

•Optimizing PHANTOM algorithm.

 

Wallet& Browser Development:

•Redesigning frame of wallet’s browser.

•Working on logical integration with the main network and mining.

 

Mining& Mine Pool Development:

•Developing power calculator module.

•Studying grin’s PoW code implementation.

•Adding cuckoo algorithm in HLC-mine.